Marathon Petroleum · Garyville, LA
Marathon Refinery — Unit 10 Revamp
Revamp of crude unit 10 with new charge pumps and upgraded ICSS.
Systems
3
Subsystems
6
Open A
2
Open B
1
MC83%
RFSU53%
Comm.37%
Handover8%
Learn: Turnover & Handover
Tap a topic — Why · How · What · Drivers. Hover any abbreviation for its meaning.
Turnover & Handover
Turnover Phases
PHASE 1
Subsystem MC certificate
PHASE 2
RFSU certificate
PHASE 3
Commissioning complete
PHASE 4
Operations acceptance
PHASE 5
Care, Custody & Control
| Subsystem | 1. Subsystem MC certificate | 2. RFSU certificate | 3. Commissioning complete | 4. Operations acceptance | 5. Care, Custody & Control | Progress | Status |
|---|---|---|---|---|---|---|---|
IA Compressor Package 20-IA · 20-IA-001 | 0% | grey | |||||
IA Dryers 20-IA · 20-IA-002 | 0% | grey | |||||
IA Distribution Network 20-IA · 20-IA-003 | 0% | grey | |||||
P-1001 A/B Train 10-PUM · 10-PUM-001 | 0% | grey | |||||
ICSS Cabinet Room 70-ICSS · 70-ICSS-001 | 60% | amber | |||||
F&G Loops Unit 10 70-ICSS · 70-ICSS-FG-10 | 0% | grey |
All changes saved
Why this matters
Operations cannot accept the entire plant in one go. Phased turnover transfers care, custody & control subsystem by subsystem. Each tick is a contractual gate.
Common field problems
Dossiers incomplete (missing as-builts, vendor manuals); operations refuses to sign because punches not reconciled; ambiguity over who maintains preservation post-MC.
Best practice
Build the dossier as you go — never at the end; require operations witnessing from MC walkdowns; export the Handover Dossier and walk it system-by-system with the asset team.