Marathon Petroleum · Garyville, LA

Marathon Refinery — Unit 10 Revamp

Revamp of crude unit 10 with new charge pumps and upgraded ICSS.

Systems
3
Subsystems
6
Open A
2
Open B
1
MC83%
RFSU53%
Comm.37%
Handover8%
Learn: Commissioning
Tap a topic — Why · How · What · Drivers. Hover any abbreviation for its meaning.

Commissioning Sequence

Commissioning Stage Map
  1. 1
    Energisation complete
    MV/LV bus, breakers, MCC tested
  2. 2
    Loop checks complete
    Field-to-DCS continuity & calibration
  3. 3
    Cause & Effect validated
    F&G/SIS interlock validation
  4. 4
    Functional test passed
    End-to-end logic & sequence
  5. 5
    Performance test passed
    Capacity & guarantee
  6. 6
    Reliability run complete
    72-hr / 7-day continuous run
Subsystem1. Energisation2. Loop3. Cause4. Functional5. Performance6. ReliabilityProgressStatus
IA Compressor Package
20-IA · 20-IA-001 · Mechanical
50%amber
IA Dryers
20-IA · 20-IA-002 · Mechanical
MC incomplete — commissioning gated
0%red
IA Distribution Network
20-IA · 20-IA-003 · Piping
33%amber
P-1001 A/B Train
10-PUM · 10-PUM-001 · Mechanical
0%grey
ICSS Cabinet Room
70-ICSS · 70-ICSS-001 · Instrumentation
100%green
F&G Loops Unit 10
70-ICSS · 70-ICSS-FG-10 · Fire & Gas
0%red
All changes saved
Why this matters
Each tick advances commissioning RAG automatically. Sequence (utilities first, then process) determines whether commissioning takes weeks or months.
Common field problems
Schedule pressure pushes process loop checks before ICSS is stable; vendors arrive after their package is needed; reliability runs start with open A-punches.
Best practice
Lock energisation order with operations and SIMOPS team; align vendor mobilisation to readiness; never enter reliability run with open A-punches.