Marathon Petroleum · Garyville, LA

Marathon Refinery — Unit 10 Revamp

Revamp of crude unit 10 with new charge pumps and upgraded ICSS.

Systems
3
Subsystems
6
Open A
2
Open B
1
MC83%
RFSU53%
Comm.37%
Handover8%
Learn: Preservation
Tap a topic — Why · How · What · Drivers. Hover any abbreviation for its meaning.

Preservation Register

SubsystemDisciplineInterval (days)Last DoneNext DueStatus
IA Compressor Package
20-IA · 20-IA-001
MechanicalActive
IA Dryers
20-IA · 20-IA-002
MechanicalNot set
IA Distribution Network
20-IA · 20-IA-003
PipingNot set
P-1001 A/B Train
10-PUM · 10-PUM-001
MechanicalActive
ICSS Cabinet Room
70-ICSS · 70-ICSS-001
InstrumentationNot set
F&G Loops Unit 10
70-ICSS · 70-ICSS-FG-10
Fire & GasNot set
All changes saved
Why this matters
Equipment in lay-up degrades — bearings flat-spot, motor windings absorb moisture, instrument transmitters drift, piping internals corrode. Failures appear at first run, weeks after MC, with no clear owner.
Common field problems
Logs stop after MC; rotating equipment not turned monthly; N₂ blanket pressure not maintained; battery rooms left without trickle charge.
Best practice
Treat preservation as a live register from delivery to start-up; assign owner per subsystem; audit monthly with operations; re-baseline preservation when systems change custody.